If the company uses activity-based costing abc how much


 

A company has identified the following overhead costs and cost drivers for the coming year:

 

 

 

 

         Budgeted

  Overhead Item

  Cost Driver

Budgeted Cost

   Activity Level

  Machine setup

  Number of setups

$ 21,000        

  200        

  Inspection

  Number of inspections

112,500        

4,500        

  Material handling

  Number of material moves

90,000        

6,000        

  Engineering

  Engineering hours

15,000        

600        

 

Budgeted direct labor cost was $190,000 and budgeted direct material cost was $530,000. The following information was collected on three jobs that were completed during the year:

 

 

Job 101

 

Job 102

 

Job 103

  Direct materials

$ 4,500

 

$ 9,500

 

$ 5,500

  Direct labor

$ 2,100

 

$ 2,100

 

$ 4,200

  Units completed

75

 

40

 

100

  Number of setups

1

 

1

 

3

  Number of inspections

15

 

8

 

10

  Number of material moves

20

 

8

 

25

  Engineering hours

8

 

40

 

5

 

If the company uses activity-based costing (ABC), how much overhead cost should be assigned to Job 101?

 

 