If management expects their rate of learning to continue


Suppose that a firm just made the first unit of a new product in 800 hours, and the second unit in 560 hours. The firm expects to complete the first 80 units this vear,. The demand next year is expected to be for 270 units. If management expects their rate of learning to continue for this product, how many total hours will be required to produce the product next year?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: If management expects their rate of learning to continue
Reference No:- TGS02587264

Expected delivery within 24 Hours