If activity e is reduced by 2 days what additional


Given the project data below, find earliest start time, earliest finish time, latest start time, latest finish time for each activity? If activity E is reduced by 2 days, what additional activities become critical?

Activity Duration Precedents

A 4 None

B 5 None

C 2 B

D 3 A, B

E 6 C, D

F 3 C, D

G 5 F

H 3 E, F

I 4 G, H