Identify the critical path and its activities for rockfest


1. Identify the critical path and its activities for Rockfest. How long does the project take?

2. Which activities have a slack time of 8 weeks or more?

3. Identify five major challenges a project manager faces in events such as this one.

4. Why is a work breakdown structure useful in a project such as this? Take the 26 activities and break them into what you think should be level-2, level-3, and level-4 tasks.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Identify the critical path and its activities for rockfest
Reference No:- TGS01665590

Expected delivery within 24 Hours