Identify the critical chain how big should be project


2202_Untitled.png

Using CCPM and the project network from question 1 to complete and answer the questions below:

a) Correctly layout the project network that should be used to help determine the Critical Chain TO SCALE and WITHOUT inserting the buffers. Use the Excel template provided to help you do so.

b) Identify the Critical Chain.

c) What is the Critical Chain duration time for Activity D?

d) Identify between which two activities each Feeding Buffer should be located (or show them inserted as properly-sized blocks into another copy of the Gantt Chart) and specify how large should each one be? What is the Critical Chain duration time for Activity D?

e) What resource buffers are needed and where should they be positioned?

f) How big should be Project buffer be and what is the total project lead time?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Identify the critical chain how big should be project