Identify all paths through the network


Problem

Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:

o Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?

o Identify all paths through the network. Which is the critical path?

o Which activities have slack time?

o Identify all burst activities and merge activities.

Textbook: Project Management by Pinto, 5th edition. ISBN: 9780134730332.

The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Project Management: Identify all paths through the network
Reference No:- TGS03122007

Now Priced at $30 (50% Discount)

Recommended (95%)

Rated (4.7/5)