With 20-20 hindsight, draw a CE (fishbone, Ishikawa) diagram to illustrate possible causes and effects. Include the possible causes mentioned in the case. The diagram should have been developed before construction, therefore also indicate other possible failure modes and other causes you can think of. How would the diagram (developed after the accident) be of value during litigation?