How would schedule x and y


"For the four basic configurations that follow, assume that the market is demanding product that must be processed by both resources x and y for cases I, II and III. For case IV, both resources supply seperate but dependent markets" that is the number of units of output for both x and y are equal. plans are being made to produce a product tht rrequires 40 minutes on resource x and 30 minutes on resource y. Assume that there is only one of each of these resources, and that market demand is 1,400 units per month. How would you schedule X and Y?