How to reduce the computation load


Discuss the below:

Q: Given the following network with activities and times estimated in days,

Activity Optimistic

Most  Probable

Pessimistic
A 2 5 6
B 1 3 7
C 6 7 10
D 5 12 14
E 3 4 5
F 8 9 12
G 4 6 8
H 3 6 8
I 5 7 12
J 12 13 14
K 1 3 4

a. Fill in all the blanks in the following table.

Note:

i) To reduce the computation load, please round the expected activity time (t)  up to an integer if the computed expected activity time is not an integer. For example, if tA=4.15, round it up to 5.

ii) For variance (σ 2) in activity time, keep two decimal places.

Activity
Precedence
Activities
Expected
Time t (days)
Variance

e σ2

ES

LS

EF

LF

Slack Critical Path?
A
B
C
D
E
F
G
H
I
J
K

b. What is the expected time and variance to complete the project?

c. What is the probability the project will take more than 28 days to complete?
Activity
Precedence
Activities
Expected
Time t (days)
Varianc

e σ2

ES

LS

EF

LF

Slack Critical Path?
A
B
C
D
E
F
G
H
I
J
K

b. What is the expected time and variance to complete the project?

c. What is the probability the project will take more than 28 days to complete?

Attachment:- Draw a network representation.rar

Request for Solution File

Ask an Expert for Answer!!
Computer Networking: How to reduce the computation load
Reference No:- TGS01863707

Expected delivery within 24 Hours