How to classify each of the april costs incurred by reynolds


Joe Reynolds painted four houses during April 2013. For these jobs, he spent $2,400 on paint, $160 on mineral spirits, and $300 on brushes. He also bought two pairs of coveralls for $100 each; he wears coveralls only while he works. During the first week of April, Reynolds placed a $200 ad for his business in the classifieds. He hired an assistant for one of the painting jobs; the assistant was paid $25 per hour and worked 50 hours.

Being a very methodical person, Reynolds kept detailed records of his mileage to and from each painting job. The average operating cost per mile for his van is $0.70. He found a $30 receipt in his van for a metropolitan map that he purchased in April. He uses the map as part of a contact file for referral work and for bids that he has made on potential jobs. He also had $30 in receipts for bridge tolls ($2 per trip) for a painting job he completed across the river.

Near the end of April, Reynolds decided to go camping, and he turned down a job on which he had bid $6,000. He called the homeowner long distance (at a cost of $2.20) to explain his reasons for declining the job.

Using the following headings, indicate how to classify each of the April costs incurred by Reynolds. Assume that the cost object is a house-painting job.

Type of cost Variable/Fixed Direct/Indirect Period/Product

Paint - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Spirits - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Brushes - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Coveralls - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Ad - (Variable,Fixed,None of above) -(Direct,Indirect,None of above) -(Period,Product,None of above)
Assistant - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Opera Costs - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) -(Period,Product,None of above)
Map --(Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Tolls - (Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)
Phone -(Variable,Fixed,None of above) - (Direct,Indirect,None of above) - (Period,Product,None of above)

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: How to classify each of the april costs incurred by reynolds
Reference No:- TGS0691039