How much would a 61 bpd plant cost when the index value is


A 24 barrel per day (bpd) fractionation tower cost $1, 152 million in 2001 when the Chemical Engineering plant cost index value was 169. How much would a 61 bpd plant cost when the index value is 494 provided the exponent in the cost-capacity equation is 0.5?