How much supervisory wages and factory supplies cost would


Use the following to answer questions

Tomasini Corporation has provided the following data from its activity-based costing accounting system:

 

Supervisory wages.............

$660,000

 

Factory supplies.................

$280,000

Distribution of Resource Consumption across Activity Cost Pools:

 

 

Activity Cost Pools

 

 

Batch Processing

Unit Processing

Other

Total

 

Supervisory wages....

20%

70%

10%

100%

 

Factory supplies........

45%

35%

20%

100%

The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products.

1. How much supervisory wages and factory supplies cost would be assigned to the Batch Processing activity cost pool?

A) $940,000

B) $470,000

C) $305,500

D) $258,000

2. How much supervisory wages and factory supplies cost would NOT be assigned to products using the activity-based costing system?

A) $122,000

B) $660,000

C) $280,000

D) $0

Request for Solution File

Ask an Expert for Answer!!
Database Management System: How much supervisory wages and factory supplies cost would
Reference No:- TGS0899835

Expected delivery within 24 Hours