How much overhead cost is allocated to the order filling


Question-

Capizzi Corporation has an activity-based costing system with three activity cost pools-Machining, Order Filling, and Other. In the first stage allocations, costs in the two overhead accounts, equipment depreciation and supervisory expense, are allocated to three activity cost pools based on resource consumption. Data used in the first stage allocations follow:
Overhead costs:

Overhead costs:

 

 

Equipment depreciation

$84,800

 

Supervisory expense

$7,300

 

 Distribution of Resource Consumption Across Activity Cost Pools:

 

Activity Cost Pools

 

Machining

Order Filling

Other

Equipment depreciation

0.50

0.40

0.10

Supervisory expense

0.50

0.30

0.20

Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow:

 Activity:

MHs (Machining)

Batches (Order Filling)

Product Y7

1,570

1,190

Product V2

9,870

2,080

Total

11,440

3,270

How much overhead cost is allocated to the Order Filling activity cost pool under activity-based costing?

a. $33,920

b. $36,110

c. $2,190

d. $74,130

Additional Requirement-

The question belongs to Basic Accounting and it illustrate about calculation of allocated overhead cost to order filling activity under activity based costing.