How much more money do you estimate you will spend to


As a manager of a software development project, you need to give senior management a report on the status of the project and a forecast for completion costs, if the project is budgeted at $100,000.00, the CPI is 0.8 and $20,000.00 of the budget has already been spend, how much more money do you estimate you will spend to complete the project.