How much money will be needed from the time of the report


The data identified below was listed in a project's latest status report:

? BCWS = $36,000

? BCWP = $30,000

? ACWP = $33,000

? BAC = $120,000

? Original length of the project 10 months

Using these data, calculate the following:

a. What are the values for CPI and SPI?

b. What is the expected cost at completion (EAC)?

c. How much money will be needed from the time of the report to complete the project?

d. What is the cost variance at completion (VAC)?

e. Using SPI, what is the new expected length of the project?