How much machines required to meet customer requirement


Discuss the below:

Q: Machining part XYX requires 3 operations in order to meet the customer requirement for 5000 parts per week. What would be the number of machines required to meet the customer requirement if the company operates 5 days a week and 15 hours per day, if:

Operation

Standard Time
(mins)

Efficiency

Reliability

Defect Rate

1

2

95%

95 %

2%

2

4

95 %

90%

2%

3

7

95 %

90 %

4%

If the Plant manager wants PM to be performed on all machines after processing lots of 250 parts, how would this affect the number of machines required ?