How much ldquoslack timerdquo is permitted in the


How much “slack time” is permitted in the “critical path” activity times?

a. Only one unit of time per activity

b. No slack time is permitted

c. As much as the maximum activity time in the network

d. As much as is necessary to add up to the total time of the project