How much does the company plan to spend


The John Fletcher Corporation manufactures mountain bikes. At the beginning of July, the Corporation had $0 beginning bikes in inventory. The Corporation expects to manufacture and sell 100 bikes in July.

  • Each bike requires a standard quantity of 3.5 direct labor hours. The standard rate per direct labor hour is $16.00
  • How much does the company plan to spend on direct labor for July?
  • Projected direct labor expenditure for July =