How much direct labor should be debited to work in process


Hoschild Bicycle Company manufacturers bicycles. The following data for September of the current year are available:

Quantity of direct labor used 850 hrs
Actual rate for direct labor $15.60 per hr
Bicycles completed in Sept 400
Standard direct labor per bicycle 2 hrs
Standard rate for direct labor $16.00 per hr

a. Determine the direct labor rate and time variances.

b. How much direct labor should be debited to Work in Process?

Solution Preview :

Prepared by a verified Expert
Cost Accounting: How much direct labor should be debited to work in process
Reference No:- TGS02524091

Now Priced at $10 (50% Discount)

Recommended (99%)

Rated (4.3/5)