How may mr beck expand capacity without purchasing new


Beck Manufacturing and Plant Capacity

Read the "Beck Manufacturing" case study in Chapter 8 of your text. Answer questions one through three in a two- to- four page paper in accordance with APA guidelines

Beck Manufacturing

Al Beck, president of Beck manufacturing, wants to determine the capacity of his facility, which produces steering gears for auto manufacturers. He has asked you to sort through the data and determine the capacity of the system and how that capacity may be increased.

The operation is a product layout that produces large numbers of nearly identical products. The process includes milling, grinding, boring, drilling, and assembling, in that order. Each finished product requires one operation on each type of machine. For example, each finished part is processed on one of the five milling machines, one of the seven grinding machines, etc.

The facility runs two 8-hour shifts per day, with a third shift for maintenance. The industrial engineering department has provided you with the following data on present operations. In addition, you have been told that assembly operations, while not unlimited, can be easily changed to meet the need.

Operation

Number of Machines

Run Time per Piece (min.)

% Reject Rate

Milling

5

2

   3

Grinding

7

3

   5

Boring

3

1

   2

Drilling

6

2.5

   7

1. Calculate the capacity of each machine center and the capacity of the system.

2. If Beck wants to expand capacity, where should he focus the company's efforts? How much extra capacity can he get without causing another operation to become the bottleneck?

3. How may Mr. Beck expand capacity without purchasing new equipment? Be specific

Your paper should be in paragraph form (avoid the use of bullet points), and supported with any formulas, calculations, and concepts outlined in your text.

Do not include the original questions of the assignment in the paper.

Solution Preview :

Prepared by a verified Expert
HR Management: How may mr beck expand capacity without purchasing new
Reference No:- TGS02329455

Now Priced at $55 (50% Discount)

Recommended (93%)

Rated (4.5/5)