Where and how many work-in-process inventory will build up in the production process shown below if each step in the process has been running at maximum capacity for 40 hours?
The process is A to B to C
Process A (8 mins)
Process B (6 units/hr)
Process C (10 units/hr)
a. 40 units between steps B and C
b. 80 units between steps A and B
c. 160 units between steps B and C
d. 60 units between steps A and B
e. 40 units before Step A