How many weeks will project take if pay crashing cost


Problem:

Bragg's loses $3500 in profit per week for every week the bakery is not completed.

Required:

How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3500?

Activity     Predecessor      N. Time(weeks)    Crash Time(weeks)       Expediting Cost/Week

    A                ---                    9                            6                              $3000

    B                A                      8                            5                                3500

    C               A                       15                         10                                4000

    D              B,C                     5                            3                                 2000

    E               C                       10                           6                                 2500

    F               D,E                     2                            1                                 5000

Solve the given numerical problem and illustrate step by step calculation.