How many weeks project take if willing to pay crashing cost


Problem:

Bragg's loses $3500 in profit per week for every week the bakery is not completed.

Required:

Question 1) How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3500?

Activity     Predecessor      N. Time(weeks)    Crash Time(weeks)       Expediting Cost/Week

    A                ---                  9                         6                            $3000

    B                A                    8                          5                            3500

    C               A                    15                         10                           4000

    D              B,C                   5                           3                            2000

    E               C                    10                          6                            2500

    F               D,E                  2                           1                            5000

Solve the problem and show all work.