A Production Process A has a fixed cost of $340,000 and a variable cost of $145 per unit. Production Process B for the same product has the fixed cost of $1,250,000 and variable cost of $95.50 per unit. How many units should be produced by Production Process B to be preferred over Production Process A? The sale price is $200 per unit.