How many teams deployed by company to complete project


Problem:

To construct an electricity generating unit, a company has to install 60 items. One team takes on an average 30 days to install one item. A team works for 300 days/year and management wants each team to have a capacity cushion 30 days per year.

Required:

How many teams have to be deployed by the company to complete the project in one year. Solve the problem and show all work.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How many teams deployed by company to complete project
Reference No:- TGS0881668

Expected delivery within 24 Hours