How many standard hours are needed to run an order of 500


How many standard hours are needed to run an order of 500 pieces if the setup time is 2.0 hours and the run time is 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency is 110% and the utilization is 85%?