How many paths are in the network and what are they


Assignment

Using the information in next Table to answer the below questions:

A) Draw the network diagram?

B) How many paths are in the network, and what are they?

C) What is the critical path and its duration?

D) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF?

Task

Duration (Days)

Predecessor/s

A

5

-

B

6

-

C

7

-

D

8

-

F

1

A

G

2

B

H

3

C

I

4

D

J

5

F,G,H

K

1

I

L

2

J

M

1

K

N

10

L,M

Format your assignment according to the following formatting requirements:

1. The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also include a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

3. Also Include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.

Solution Preview :

Prepared by a verified Expert
Management Information Sys: How many paths are in the network and what are they
Reference No:- TGS02950061

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)