How many labor hours are required for the fifteenth


You need to develop a labor time estimate for a customer order of 20 network installations. it is estimated that the first installation will require 60 hours of labor and a learning curve of 90 percent is expected.

a. How many labor hours are required for the fifteenth installation?

b. How many labor- hours are required for the twentieth installation?

c. How many labor-hours are required to complete all 20 installations?

d. If the average labor cost is $32, what is the total labor cost for installing the networks