How many kanbans are needed for the packaging center


A manufacturer of thermostats uses a kanban system to control the flow of materials. The packaging center processes 10 thermostats an hour and receives completed thermostats every 30 minutes. Containers hold 5 thermostats each. How many kanbans are needed for the packaging center?