How many kanban production cards are needed how many hours


Consider the following information:

Demand rate (D) = 200 units per hour Lead time (T) = 12 hours

Container capacity (C) = 144 units Safety factor (x) = 15%

a. How many kanban production cards are needed?

b. How many hours' worth of demand will these cards represent?

c. Suppose the container size is cut in half. Will this make any difference in the inventory levels? Show your work.