How many days must every plant be planned to fill order


Kitchen Korner makes refrigerators, dishwashers, and stoves at 3 different factories. Table provides number of every product produced at every factory per day. Kitchen Korner gets the order for 110 refrigerators, 150 dishwashers and 114 ovens. How many days must every plant be scheduled to fill order?

Appliance Factory A Factory B Factory C

Refrigerators 8 10 14

Dishwashers 16 12 10

Stoves 10 18 6