How long will this project take how sensitive is the


You are creating a customer database for Winston-Salem Warthogs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncriticalactivities.

 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How long will this project take how sensitive is the
Reference No:- TGS0563870

Expected delivery within 24 Hours