How long must the cycle length be so that the queue that


An approach to a signalized intersection has a displayed green time of 35 seconds, and all-red time of 2 seconds, a yellow time of 3 seconds, and a total lost time of 3 seconds.

The arrival rate is v(t) = 0.5 + 0.002t [with v(t) in veh/s and t in seconds measured from the beginning of the effective red of the cycle]. The saturation flow rate of the approach is 3400 veh/h.

How long must the cycle length be so that the queue that forms at the beginning of the cycle (effective red) dissipates exactly at the end of the cycle (end of the effective green) and what would be the average delay per vehicle over the cycle?

(Assume D/D/1 queuing.)