Hich activities should be crashed to meet a project


Crashing Problem

Use the network diagram below and the additional information provided to answer the corresponding questions. (only worry about the direct costs shown here. Don’t worry about any indirect costs)

a) Give the crash cost per day per activity.

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?

c) Find the new budget (or cost of the project).