Helvey argues that providing electrical energy is not a


Helvey brought suit against the Wabash County REMC (REMC) for breach of implied and express warranties. He alleged that REMC furnished electricity in excess of 135 volts to Helvey's home, damaging his 110-volt household appliances. This incident occurred more than four years before Helvey brought this suit.

In defense, REMC pleads that the Uniform Commercial Code's (UCC's) Article 2 statute of limitations of four years has passed, thereby barring Helvey's suit.

Helvey argues that providing electrical energy is not a transaction in goods under the UCC but rather a furnishing of services that would make applicable the general contract six-year statute of limitations. Is the contract governed by the UCC? Why?

Request for Solution File

Ask an Expert for Answer!!
Management Theories: Helvey argues that providing electrical energy is not a
Reference No:- TGS02174192

Expected delivery within 24 Hours