He should approach the senior management and ask


Mr. SURESH is the Project manager for a Defiance project. The scope of the project has been completed. He receives a request for a new module to be developed as part of this project. What should he do next? Which option he would select and why? What is the reason for ignoring remaining options? 
a.He should approach the Senior Management and ask them for a new module to be developed as part of this project. 
b.He should send the request to Change Control Board for approval. 
c.Since the project scope is completed, he should inform the customer that this change cannot be done as part of the project.

Request for Solution File

Ask an Expert for Answer!!
Basic Computer Science: He should approach the senior management and ask
Reference No:- TGS0137791

Expected delivery within 24 Hours