Harley davidson makes motorcycle engines in its milwaukee


Question - Harley Davidson makes motorcycle engines in its Milwaukee plant. For the most recent month, budgeted production was 3,300 engines. The standard power cost is $9.20 per machine-hour. The company's standards indicate that each engine requires 2.1 machine-hours. Actual production was 3,400 engines. Actual machine-hours were 7,160 machine-hours. Actual power cost totaled $61,815.

a) What is the rate variances for the variable overhead item power cost?

b) What is the efficiency variance of the variable overhead item power cost?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Harley davidson makes motorcycle engines in its milwaukee
Reference No:- TGS02382060

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)