given the subsequent production plan use a-a


Given the subsequent production plan, use a-

(a) Chase production strategy

(b) Level production strategy to calculate the monthly production, ending inventory/(backlog) and workforce levels.

A worker is proficient of producing 100 units per month. Assume the beginning inventory as of January is zero, and the firm wants to have zero inventory at the end of June.

MONTH            JAN    FEB   MAR    APR    MAY   JUN

Demand         2000   3000  5000   6000   6000  2000

Production

Ending Inventory

Workforce