Given the project within the table below calculate athe


Given the project within the table below calculate

a.The critical path

b.The minimum project duration

c. The amount of slack for each activity

Activity

Duration (hours)

Immediate Predecessors

A

4

None

B

3

None

C

10

None

D

7

B,C

E

1

D

F

1

E

G

5

A,F