Given the project data below which activities are critical


Given the project data below, which activities are critical and what is the length of the critical path? If activity E is reduced by 2 days, what additional activities become critical?

Activity Duration Precedents

A 4 None

B 5 None

C 2 B

D 3 A, B

E 6 C, D

F 3 C, D

G 5 F

H 3 E, F

I 4 G, H

 