Given the network plan that follows compute the early late


Given the network plan that follows, compute the early, late, and slack times. What is the project duration? using any appraoch you wish ( e.g., trial and error), develop a loading chart for resourses, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exsists. Given your resource schedule, compute the early, ;ate, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects? 1391_media_6ff_6ff7768b-3e4f-42a9-84fe-bb262beef106_phpgtfC8K.png