Given the following information with demand and performance


Given the following information with demand and performance cycle certainty:           

Average daily demand = 40 units                                                                                   

Performance cycle = 10 days                                                                                                                             

Order quantity (from (EOQ) = 400 units                                                                                               

Review period = 2 weeks (10 working days)

Calculate:                                                                                                       

a) the reorder point utilizing the perpetual review method

b) the reorder point utilizing the periodic review method