Given the following information what cycle time must be


Marketing would like production to make 282 musical hula hoops per 7.3 hour day.

Given the following information, what cycle time must be achieved to meet that demand?

Total Task Time (minutes) = 31

Longest Task Time (minutes) = 3.2

Number of machines = 33

(Your answer should be in seconds and have one decimal place.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Given the following information what cycle time must be
Reference No:- TGS02496311