Given the following information for a cost project project


Given the following information for a COST project: Project A: NPV -$210K; Project B NPV -$175K, Project C NPV -$165K. Comparing the Alternatives C-A gives IRR of 20%, B-C gives IRR of 28% (the MARR used is 5%). If using NPV projects ranked are C>B>A, if using IRR Project Rank B>C>A. Which project should you pick and why?