Given the data in the table construct a 3-sigma c-chart


After the stamping operation, door panels are periodically selected for a detailed examination in which the number of surface scratches, dents, and other flaws are counted. During today's production run, 20 panels were inspected.

Given the data in the table, construct a 3-sigma c-chart, then reach a conclusion regarding whether the process is in control.

919_Tab.jpg

Request for Solution File

Ask an Expert for Answer!!
Project Management: Given the data in the table construct a 3-sigma c-chart
Reference No:- TGS02206702

Expected delivery within 24 Hours