Frances is the project manager of the jhg project this


Frances is the project manager of the JHG Project. This project is very similiar to a recent project she completed for another customer.. Which planning process will Frances need to finish first to ensure the project is completely successfully?

a. contract planning

b. scope definition self test

c. activity sequencing

d. quality planning