Formulate-solve linear programming model to minimize cost


EZ-Windows, Inc., manufactures replacement windows for the home remodeling business. In January, the company produced 15,000 windows and ended the month with 9000 windows in inventory. EZ-Windows management team would like to develop a production schedule for the next three months. A smooth production schedule is obviously desirable because it maintains the current workforce and provides a similar month-to-month operation. However, given the sales forecasts, the production capacities, and the storage capabilities as shown, the management team does not think a smooth production schedule with the same production quantity each month possible.

February March April
Sales forecast 15,000 16,500 20,000
Production capacity 14,000 14,000 18,000
Storage capacity 6,000 6,000 6,000

The company's cost accounting department estimates that increasing production by one window from one month to the next will increase total cost by $1.00 for each unit increase in the production level. In addition, decreasing production by one unit from one month to the next will increase total costs by $0.65 for each unit decrease in the production level.

Ignoring production and inventory carrying costs, formulate and solve a linear programming model that will minimize the cost of changing production levels while still satisfying the monthly sales forecasts.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Formulate-solve linear programming model to minimize cost
Reference No:- TGS085112

Expected delivery within 24 Hours