For the purpose of preparing the flexible budget what is


Question - Lewis Marine Company manufactures special metallic materials and decorative fittings for luxury yachts that require highly skilled labor. Lewis uses standard costs to prepare its flexible budget. For the first quarter of the year, direct materials and direct labor standards for one of their popular products were as follows:

Direct materials: 4 pounds per unit; $6 per pound

Direct labor: 2 hours per unit; $19 per hour

During the first quarter, Lewis produced 5,000 units of this product. Actual direct materials and direct labor costs were $65,000 and $331,000, respectively.

For the purpose of preparing the flexible budget, what is the total standard direct labor cost at a production volume of 5,000 units?

(a) $95,000

(b) $65,000

(c) $190,000

(d) $331,000

Solution Preview :

Prepared by a verified Expert
Accounting Basics: For the purpose of preparing the flexible budget what is
Reference No:- TGS02407403

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)