For the project with uncertain activity times given below


For the project with uncertain activity times given below, do the following manually:

(a) Develop a resource schedule based on the ACTIM heuristic and indicate the project completion time,

(b) Draw a Gantt chart, and

(c) Draw a resource loading chart for each resource type.

You will have to perform the PERT/CPM calculations first. Assume the total number of identical, full-time Type 1 resources available initially = 10, and Type 2 resources initially .

An activity can start only when all required units of both resource types are available at the same time.

ACTIVITY

Type 1 Resource Required

Type 2 Resource Required

Predecessor

Optimistic

Most Probable

Pessimistic

A

3

0

-

4

5

6

B

5

4

-

8

9

10

C

4

1

A

7

7.5

11

D

2

0

B

7

9

10

E

4

3

B

5.5

7

9.5

F

2

7

D

5

6

7

G

6

2

E

6

7

8

Solution Preview :

Prepared by a verified Expert
Business Management: For the project with uncertain activity times given below
Reference No:- TGS01676310

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)