For the following payoff table determine the expected


For the following payoff table, determine the expected value of perfect information. Does the result seem unusual? If so, why did this occur?

 

State of Nature

 

I(0.6)

II(0.4)

Alternative A

$80

$30

Alternative B

$12

$20